Your Vehicle: 2000 Volvo S80 T6 L6-2.8L Turbo VIN 90 B6284T
       
 
Vehicle » Engine, Cooling and Exhaust » Engine » Service and Repair » Engine/Transmission In icon_note_blank.gif  Notes
 
 
  Engine/Transmission In  
 

Raising Into Engine Compartment With Sub-Frame

Special Tools
951 2050
999 5972
999 5722

Installing engine/transmission unit

  

Lift up the engine/transmission unit. Use a lifting table.
Stop the lift approximately 15 cm (5.91 inch) before the sub-frame reaches the frame members.

Note: Make sure that the mating surfaces on the ball joints and control arms are clean. Take great care that no hoses, wiring or anything else catches during lifting.

Install (on both sides)

  • the drive shaft to the hub.
  • the ball joint to the control arm. Guide in the lower steering shaft in the boot.

Lift the subframe to the frame members.

  

Install new screws in the sub-frame. Oil/lubricate screw threads.
Install washers in the front edge and support plates at the rear edge of the sub-frame.
First tighten the screws on the left-hand side of the subframe to 105 Nm (77.4 ft. lbs.) and angle-tighten 1200.
Use bevel protractor 951 2050.
Then tighten screws on right-hand side of sub-frame to the same value.
Tighten the brackets to 50 Nm (36.9 ft. lbs.) .
Remove lifting table.

Install the catalytic converter unit
Use the new nuts and gaskets.

Note: Lubricate threads with paste, P/N: 1161408.

  

Connect the pipe to the engine. Use a mobile jack with universal plate 999 5972 as support.

Note: Ensure that the heated oxygen sensor (H02S) wiring is on top of the brake pipe.

Connect to rear exhaust pipe. Install all nuts loosely.
Install screws in front SIPS member.
Remove the mobile jack.
First tighten the exhaust pipe flange to the engine. Then tighten the rear flange. Tighten crosswise to 25 Nm (18.4 ft. lbs.) .
Install rear SIPS member.
Tighten the SIPS member screws to 25 Nm (18.4 ft. lbs.) .

  

(The illustration is not accurate because the pulsed secondary air injection system (PAIR) pump is discontinued).
Connect heated oxygen sensors (H02S) connectors according to markings made earlier.
Secure heated oxygen sensor (H02S) wiring in sub-frame.
Press the brake pipe into place on the front SIPS member.

Install

  • the lower oil cooler hose to the transmission.
  • lower radiator hose.

  

Tighten the ball joint/control arm to 80 Nm (59.0 ft. lbs.) .
Counterhold with Torx. 40 so that the ball joint boot does not rotate.

Install

  • tie rods. Use new locknuts. Tighten to 70 Nm (51.6 ft. lbs.) .
  • the anti-roll bar links. use new locknuts. Tighten to 50 Nm (36.9 ft. lbs.) .
  • new center screws for the drive shafts. Tighten to 50 Nm (36.9 ft. lbs.) .
  • ABS sensors. Tighten to 10 Nm (7.3 8 ft. lbs.) .

Note: Ensure that the ABS sensor seats are absolutely clean.

  • the ABS sensor cable to the mounting in the spring strut.
  • the brake pipe racket in the wheel arch.

Install

  

  • front splash guard.
  • the splash guard under the engine.
  • wheels.

  

  • the bearing in the lower steering shaft. Secure it in the rubber boot with a tie strap.
  • the steering shaft joint in the lower steering shaft. Use a new screw and locknuts. Tighten to 30 Nm (22.1 ft. lbs.) .

Note: Previous measurement for correct steering gear position.

  • panel under dashboard.

  

  • Air conditioning (A/C) compressor Tighten to 25 Nm (18.4 ft. lbs.) .
  • connector to the dryer bottle.
  • the magnetic clutch connector with the engine wiring.
  • auxiliaries belt.
  • the hose between the charge air cooler (CAC) and turbocharger (TC) pipe. Applies only to B6xx4T.
  • upper radiator hose.

  

Connect engine and transmission wiring connectors in control module box base plate.
Press base plate into place in lower section of control module box.
Install intermediate section.
Locate ventilation pipe in rear edge of control module box.
Screw control module box into place on fender liner.
Press control modules down carefully. Lock with mounting bracket 999 5722.
Press the cover into place and the screw ground lead into place.

Install

  

  • expansion tank. Connect the hose from the radiator to the expansion tank.
  • the servo reservoir.

  

  • the fan shroud on the radiator.
  • the connectors to the engine cooling fan (FC) , canister purge (CP) valve and pulsed secondary air injection system (PAIR) PUMP.
  • the wiring to the terminal block. Secure wiring.

  

  • the charge air pipe to the charge air cooler (CAC). Applies only to B6xx4T.
  • the upper oil cooler hose to the transmission.
  • the transmission cable to the transmission.
  • the air intake pipe to the air cleaner (ACL) housing in the fan shroud.
  • the brake servo hose to the intake manifold.
  • the air cleaner (ACL) housing with all connections.

  

  • the positive cable to the positive terminal block.
  • cross stay pipe between suspension turret. Tighten to 50 Nm (36.9 ft. lbs.) .
  • torque rod mounting on engine. Use a new screw and locks. Tighten to 80 Nm (59.0 ft. lbs.) .
  • the battery negative lead. First read Note when disconnecting / connecting the battery lead.

Final Check
Top up

  

  • coolant. Coolant volume approximately 7.2 liters (1.9 us gal.) .
  • engine oil.

Start the engine. Warm up engine to thermostat opening.
Check for leakage.
Check oil and coolant levels. Adjust if necessary.

Applies to cars with automatic transmission:
Check transmission oil level.